JTC Surface Finishing Complex
Description: Main Contract Works for Proposed 4-Storey Multi-Tenanted Suface Finishng Complex with a Central Waste Treatment Plant Building and Ancillary Works along Jalan Buroh in Tanjong Kling (Sector 2)
Contract Value: $46m
Main Components:Building Works; Structural Steel Works; Mech'l & Elec'l Works; Sanitary & Plumbing; External Works
Status: Main Contractor (MC)
Commencement and Completion Date: 16 April '12 - 22 October'13
( 18 months)
Client: JTC Corporation
30 Tuas View Square
Description: Proposed Erection of Multiple-user General Industrial Development Comprising 10units of 3-Storey Terrace Factory
Contract Value: $5m
Main Components: Building Works; Structural Steel Works; Mech'l & Elec'l Works;Sanitary & Plumbing; External Works
Status: Main Contractor (MC)
Commencement and Completion Date: 02 July '12 - 29 October 13
( 16 months)
Client: SCB Tuas Pte Ltd
Meissa at Pasir Panjang
Description: Erection of a 7-Storey Multiple-User Light Industrial Development with a Basement Car Park (Total:58 Factory Units) on Lot 00576L MK 03 at 100-D Pasir Panjang Road (Queenstown Planning Area)
Contract Value: $15m
Main Components: Building Works; Structural Steel Works; Mech'l & Elec'l Works; Sanitary & Plumbing; External Works
Status: Main Contractor (MC)
Commencement and Completion Date: 19 July '10 - 18 June '11 (11 months)
Client: Orion-Five Development Pte Ltd